Concrete Calculator
Work out how much concrete a slab, footing or column needs, in cubic yards and bags of premixed concrete, with extra for waste and the cost.
- Free, no sign-up
- Runs in your browser
- Sources cited
- Slab, patio or driveway
- Footing or wall
- Round column or post hole
Bags and prices
- 40 lb bag
- 50 lb bag
- 60 lb bag
- 80 lb bag
- 90 lb bag
Concrete needed
- Cubic yards
- 80 lb bags
- Cubic feet
- 36.67
- Cubic meters
- 1.04
Bags of each size
| Bag | Yield per bag | Bags |
|---|---|---|
| 40 lb bag | 0.30 ft³ | 123 |
| 50 lb bag | 0.375 ft³ | 98 |
| 60 lb bag | 0.45 ft³ | 82 |
| 80 lb bag | 0.60 ft³ | 62 |
| 90 lb bag | 0.675 ft³ | 55 |
Step by step
Thickness (inches) in feet: inches ÷ 12
Length × width × thickness
Plus 10%
Cubic yards: cubic feet ÷ 27
How to use the concrete calculator
Choose the shape
A slab, patio or driveway; a footing or wall; or round columns and post holes.
Enter the size and how many
Lengths in feet and thicknesses in inches, as they are usually measured, and the number of identical pieces.
Add extra and prices
Keep or change the extra for waste, choose a bag size, and add a price per bag or per cubic yard to see the cost.
Read the result
See the volume in cubic yards, feet and meters, the bags of each size you need, and the cost. Click a figure to see the working.
How concrete is measured
Volume is length times width times thickness, with every measurement in feet: inches are divided by 12. A round column is π times the radius squared times its height. The result in cubic feet is multiplied by the number of pieces and by one plus the waste allowance, then divided by 27 for cubic yards, since a cubic yard is three feet on each side. Cubic meters use the NIST conversion factor for a cubic foot.
For bagged concrete, the volume is divided by what one bag makes and rounded up to whole bags. QUIKRETE states on its Concrete Mix data sheet that a 40 lb bag yields about 0.30 cubic feet, a 60 lb bag about 0.45 and an 80 lb bag about 0.60; other brands are similar but not identical, so check the bag.
The waste allowance covers spillage, uneven ground and forms that bow under the weight of wet concrete. Ready-mix concrete is ordered by the cubic yard, while bags suit small pours you mix yourself.
Worked example
A slab 10 feet by 10 feet and 4 inches thick holds 33.33 cubic feet. With 10% extra that is 36.67 cubic feet, or 1.36 cubic yards: 62 bags of the largest common size, or 123 of the smallest.
A column 12 inches across and 4 feet deep holds 3.14 cubic feet; 4 of them, with the same extra, take 24 large bags.
Understanding the result, and common mistakes
- Mixing units. Lengths are in feet and thicknesses in inches; a 4-inch slab is a third of a foot thick, not four feet.
- Ordering exactly the volume. Running short mid-pour leaves a weak joint, so order the extra.
- Forgetting gravel or rebar. The calculator counts concrete only; the base and reinforcement are separate.
- Assuming every bag yields the same. Check the yield printed on the brand you buy.
Frequently asked questions
How many bags make a cubic yard?
A cubic yard is 27 cubic feet, so it takes 45 bags at 0.60 cubic feet per 80 lb bag, or 90 bags at 0.30 per 40 lb bag, before any waste.
How much extra should I order?
The calculator starts at 10%. Raise it for uneven ground or complex forms, and lower it for small, simple pours on even ground.
Can I see how the volume was worked out?
Yes. Click the cubic yards or the bags to see each step.
Is anything I enter sent anywhere?
No. The calculator runs in your browser.
Sources
- QUIKRETE Concrete Mix (No. 1101) product data sheetQUIKRETE · retrieved Nov 15, 2026
- NIST Guide to the SI, Appendix B.8: Factors for units listed alphabeticallyNational Institute of Standards and Technology · retrieved Nov 15, 2026
About these results
- Estimates for planning. Bag yields are a manufacturer’s approximate figures; check the bag and local requirements before you pour.
- The calculator runs in your browser. Nothing you enter is sent anywhere.